Arecibo–Rome Railway
The company’s role begins as a designer or a contracting firm, starting from the project’s initial vision and developing it into a detailed design concept. This is followed by planning and execution, continuing until the project is fully completed and delivered in the best possible condition — ensuring customer satisfaction and encouraging clients to return.
Quantities executed by the group:
- Ordinary and reinforced concrete works:
- 10,000 m³ for villas and low-rise buildings
- 40,000 m³ for multi-storey residential buildings
- 24,000 m³ for administrative buildings with reinforced foundations
- 50,000 m³ of ready-mix concrete supplied and poured on-site
- 20,000 m³ for residential buildings
- 30,000 m³ for piles and industrial/administrative buildings
- 16,000 m³ for cement development and masonry works
- 23,000 m³ for plastering and façade finishing works
- Carpentry works:
- Approximately 9,000 wooden pieces
- Metal works and steel structures:
- Metal works, wrought iron, and steel frame structures